MODOT Construction Week Of August 3rd

Nodaway County

Route 46 – CLOSED for a bridge replacement project at the White Cloud Creek Bridge, east of Route AB, and Stream Bridge, west of Route AB. The project to replace all four bridges is expected to continue through early December. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/route-46-bridge-projects-west-maryville

Route Y – Pothole patching south of Route A, Aug. 3

Route AH – Pothole patching, Aug. 4 – 5

Andrew County

Route 48 – CLOSED for a bridge replacement project over Agee Creek. The bridge is expected to reopen Aug. 10. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. More info: https://www.modot.org/andrew-county-route-48-bridge-replacement-over-agee-creek

Interstate 29 – Bridge replacement project over Hopkins Creek and Route T (mile marker 58-60) through January 2021. A 14-foot width restriction is in place. These bridges are included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

Route Y – CLOSED for a culvert replacement from County Road 4 to County Road 7 through Aug. 3 at 4:30 p.m.

U.S. Route 59 – Culvert replacement at County Road 62, Aug. 6, 6 a.m. to 4:30 p.m. The entrance to County Road 62 will be closed while work is ongoing. Flaggers will be in place on U.S. Route 59 to guide motorists through the work zone.

Atchison County

U.S. Route 59 – Roadside work at Route B, Aug. 3

Routes B and C – Pothole patching, Aug. 3 – 7

Route 275 – Drainage work west of Route CC, Aug. 4 – 7

Gentry County

Route O – CLOSED for a culvert replacement from County Road 507 to Route YY, Aug. 5, 7 a.m. to 2 p.m.

Holt County

U.S. Route 159 – CLOSED for a bridge replacement project at the Penny Slu Bridge through mid-August. More info: https://www.modot.org/penny-slu-bridge-replacement-and-i-29-overpass-redeck-project

Route T – CLOSED for a bridge replacement project over Easter Creek near Oregon through late August. This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

Route T – CLOSED for a slide repair project near Mill Bluff Road, south of Forest City, through August. More info: https://www.modot.org/holt-county-route-t-slide-repair-job

I-29 – Bridge deck replacement project over Route E and Kimsey Creek through mid-September. These bridges are included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state. A 16-foot width restriction is in place.

Worth County

Route C – CLOSED pavement repair from Route M to Gentry Worth Road, Aug. 3, 7 a.m. to 4 p.m.

Route C – Scrub seal project from Route M to Gentry Worth Road, Aug. 4